KATINGAN RIA THERMAL COAL TO START PRODUCTION FROM EARLY 2014
COALspot.com - Realm Resources Ltd. (ASX: RRP) has announced the completion of the Feasibility Study for its 51% owned Katingan Ria thermal coal project (the “Project”) in Central Kalimantan, Indonesia.
According to the company’s report to ASX Limited, the study, independently reviewed by Xenith Consulting Pty. Limited (“Xenith”), supports the development of a 2.5 million tons per annum (Mtpa) (Base case) to 3.0Mtpa (Upside case) open cut mine with a life of mine of around fifteen years. The study was based on coal being hauled 40km - 45km to a stockpiling and barge loading facility on the Katingan River, then barged 435 km to the river mouth for transhipment into ships for delivery to market. The coal is expected to be predominately sold as a low ash and low sulphur coal ideally suited for modern Indian and Chinese power generation.
The Katingan Ria coal project is located near the town of Tumbang Samba in Central Kalimantan, Indonesia. The Project mining concession covers an area of some 4,258 ha within an area that has already been subject to commercial forestry operations (IUP Exploitation No. IUP OP No. 545/222/KPTS/VIII/2011). The Project aims to be a 2.5Mtpa – 3.0Mtpa open cut mine. Coal is transported from the pit by 60 t road trucks approximately 40km - 45 km to a stockpiling and barge loading facility on the Katingan River. Barges will then transport coal 435 km to the river mouth for transhipment into coal ships for delivery to market.
Coal will be sold “unwashed”, meaning there is no metallurgical treatment required to achieve a saleable product. The coal is expected to be predominately sold as a low ash and low sulphur coal ideally suited for modern Indian and Chinese power generation, the company’s announcement said.
HIGHLIGHTS
- Near horizontal, multi-seam coal deposit with JORC resources of 89Mt, including JORC reserves of 29Mt assuming a long term coal price of USD52/ton for the expected Katingan Ria coal quality;
- Indicative product specifications are consistent with Indonesian 4,200kcal/kg (GAR) low sulphur (0.2%) coal which is readily accepted in rapidly growing markets in India, China, Korea and Thailand;
- Low project start-up capital estimate of USD24M (including 30% contingency and USD6M working capital), implying a capital intensity of less than USD10/annual ton, thereby minimising investment risk;
- Life of mine (LOM) FOB cash costs of ~USD41/t (Base case) to ~USD39/t (Upside case) excluding royalties with the first five years averaging ~USD38/t due to lower strip ratios and haulage distances;
- NPV (100%) of USD78M (Base case) to USD111M (Upside case) at a 10% discount rate is most sensitive to coal price and operating costs and least sensitive to capital expenditure;
- Permitting is well advanced, supporting forecast production and ramp up from early 2014.
Commenting on the study, Chairman Richard Rossiter said, “We are pleased to achieve another key milestone as we progress Katingan Ria towards production in 2014. Together with our partners, we are now focused on advancing the final stages of permitting, and project financing and development”.
The Project is not capital intensive, with a total of USD18.5M required to establish a 2.5Mtpa to 3.0Mtpa contractor driven operation. An additional USD6M is required for working capital. Base case FOB cash costs are forecast to be USD37.62/t in the first five years with an average USD41.23/t over the life of mine (excluding royalties). Including royalties, FOB cash cost forecasts are USD 39.37/t and USD 42.68/t respectively. The average life of mine FOB cash cost in the Upside case is around USD2/t lower due to economies of scale. Permitting is in the final stages, and production is forecast as early as H1 2014, the company said in its report.
The Project is well advanced and has a high level of support from the local community and government. The balance of 49% of PTKR is held by professional Indonesian partners.
According to company, the company has identified following strengths for the project:
- The deposit (89.9Mt JORC resource, 29Mt JORC reserve) is structurally simple with a low strip-ratio, therefore leading to lower mining costs.
- The coal (4,200 GAR Kcal/kg raw coal basis) is relatively homogenous, low in sulphur (0.2%) and most likely to be marketed to the rapidly growing demand centres in India, China, Korea and Thailand.
- Low start-up capital.
- The Project requires no rail or port infrastructure to be developed and therefore could be bought into production relatively quickly.
- The key technical risks for the Project are:
- FOB cost factors associated with river seasonality and the transport distance to the coast.
- Margins received from the sale of the coal are very sensitive to coal price assumptions and potential increases in operating costs.
About Realm
Realm’s strategy is to create shareholder value through exploration and development of bulk commodity projects, primarily in coal. In addition, the Company has platinum group metals, advanced exploration projects and an aluminium dross treatment plant in South Africa.
If you believe an article violates your rights or the rights of others, please contact us.
|
|
Thursday, 07 February 13
CHINA NDRC APPROVED 10 BILLION YUAN POWER GENERATION PROJECTS
NDRC of China currently announced that some of power grid and power station in Jiangxu, Sichuan and Anhui Province would be newly constructed or ext ...
Thursday, 07 February 13
CAPESIZE : MORE ACTIVE WEEK IN THE PACIFIC - FEARNLEYS AS
Handy
The Atlantic market remained stable with no significant movement in rates. Rates from USG to FEast were around USD 18k and Black Sea to Feast ...
Thursday, 07 February 13
WEAK STEEL MARKET MEANS IRON ORE RALLY LIKELY TO END SOON - FITCH
The sharp rebound in iron ore prices over the last couple of months will hurt margins at non-integrated steel producers in the first quarter of 2013 ...
Tuesday, 05 February 13
THE SHIPPING SECTOR IS " NAVIGATING IN STORMY WATERS" - PWC
The vulnerabilities of the global economy have been exposed and have more than played their part in making 2011 one of the worst years of shipping i ...
Tuesday, 05 February 13
NEWCASTLE PORT COAL SHIPMENTS DROPPED BY 10.77 PERCENT W-O-W
COALspot.com - Newcastle port in Australia has loaded 2,412,497 MT of thermal and coking coal for week ended 0700 hours 4 February 2013, Newca ...
|
|
|
Showing 4391 to 4395 news of total 6871 |
|
 |
|
|
|
|
| |
|
 |
|
|
| |
|
- Global Business Power Corporation, Philippines
- International Coal Ventures Pvt Ltd - India
- Agrawal Coal Company - India
- Straits Asia Resources Limited - Singapore
- Kobexindo Tractors - Indoneisa
- CNBM International Corporation - China
- Kepco SPC Power Corporation, Philippines
- Intertek Mineral Services - Indonesia
- Rio Tinto Coal - Australia
- Coal and Oil Company - UAE
- VISA Power Limited - India
- Goldman Sachs - Singapore
- Samtan Co., Ltd - South Korea
- Aditya Birla Group - India
- Karaikal Port Pvt Ltd - India
- Sinarmas Energy and Mining - Indonesia
- Madhucon Powers Ltd - India
- Tata Chemicals Ltd - India
- PNOC Exploration Corporation - Philippines
- Maheswari Brothers Coal Limited - India
- Planning Commission, India
- Karbindo Abesyapradhi - Indoneisa
- Pendopo Energi Batubara - Indonesia
- SMG Consultants - Indonesia
- MS Steel International - UAE
- Rashtriya Ispat Nigam Limited - India
- Toyota Tsusho Corporation, Japan
- Bank of Tokyo Mitsubishi UFJ Ltd
- Barasentosa Lestari - Indonesia
- Renaissance Capital - South Africa
- Carbofer General Trading SA - India
- Grasim Industreis Ltd - India
- CIMB Investment Bank - Malaysia
- Dalmia Cement Bharat India
- Eastern Coal Council - USA
- Orica Australia Pty. Ltd.
- London Commodity Brokers - England
- Sarangani Energy Corporation, Philippines
- GAC Shipping (India) Pvt Ltd
- Indogreen Group - Indonesia
- Global Coal Blending Company Limited - Australia
- Altura Mining Limited, Indonesia
- Standard Chartered Bank - UAE
- Iligan Light & Power Inc, Philippines
- The State Trading Corporation of India Ltd
- Essar Steel Hazira Ltd - India
- Videocon Industries ltd - India
- Salva Resources Pvt Ltd - India
- Mercuria Energy - Indonesia
- Independent Power Producers Association of India
- Indian Oil Corporation Limited
- Africa Commodities Group - South Africa
- PetroVietnam Power Coal Import and Supply Company
- Trasteel International SA, Italy
- Simpson Spence & Young - Indonesia
- Chamber of Mines of South Africa
- Global Green Power PLC Corporation, Philippines
- Edison Trading Spa - Italy
- Bukit Makmur.PT - Indonesia
- Kartika Selabumi Mining - Indonesia
- Ministry of Finance - Indonesia
- Georgia Ports Authority, United States
- European Bulk Services B.V. - Netherlands
- Xindia Steels Limited - India
- Borneo Indobara - Indonesia
- ASAPP Information Group - India
- Merrill Lynch Commodities Europe
- South Luzon Thermal Energy Corporation
- Riau Bara Harum - Indonesia
- Australian Coal Association
- Marubeni Corporation - India
- Central Electricity Authority - India
- Gujarat Sidhee Cement - India
- Energy Development Corp, Philippines
- Tamil Nadu electricity Board
- Commonwealth Bank - Australia
- Ministry of Transport, Egypt
- Electricity Authority, New Zealand
- Metalloyd Limited - United Kingdom
- Dong Bac Coal Mineral Investment Coporation - Vietnam
- Bulk Trading Sa - Switzerland
- Kohat Cement Company Ltd. - Pakistan
- Cigading International Bulk Terminal - Indonesia
- Gujarat Electricity Regulatory Commission - India
- Electricity Generating Authority of Thailand
- Minerals Council of Australia
- TNB Fuel Sdn Bhd - Malaysia
- Bangladesh Power Developement Board
- Mintek Dendrill Indonesia
- Sical Logistics Limited - India
- Ambuja Cements Ltd - India
- IHS Mccloskey Coal Group - USA
- Kapuas Tunggal Persada - Indonesia
- Bhatia International Limited - India
- Bhoruka Overseas - Indonesia
- Ceylon Electricity Board - Sri Lanka
- Anglo American - United Kingdom
- India Bulls Power Limited - India
- Coastal Gujarat Power Limited - India
- Interocean Group of Companies - India
- Bahari Cakrawala Sebuku - Indonesia
- Deloitte Consulting - India
- Semirara Mining and Power Corporation, Philippines
- Economic Council, Georgia
- Indian Energy Exchange, India
- GMR Energy Limited - India
- PTC India Limited - India
- Aboitiz Power Corporation - Philippines
- Siam City Cement PLC, Thailand
- Sree Jayajothi Cements Limited - India
- Thiess Contractors Indonesia
- Petron Corporation, Philippines
- Singapore Mercantile Exchange
- SMC Global Power, Philippines
- Chettinad Cement Corporation Ltd - India
- Gujarat Mineral Development Corp Ltd - India
- Larsen & Toubro Limited - India
- Eastern Energy - Thailand
- GN Power Mariveles Coal Plant, Philippines
- Coalindo Energy - Indonesia
- Thai Mozambique Logistica
- McConnell Dowell - Australia
- Dr Ramakrishna Prasad Power Pvt Ltd - India
- Heidelberg Cement - Germany
- San Jose City I Power Corp, Philippines
- Petrochimia International Co. Ltd.- Taiwan
- Lanco Infratech Ltd - India
- Vizag Seaport Private Limited - India
- Posco Energy - South Korea
- The University of Queensland
- Krishnapatnam Port Company Ltd. - India
- Mercator Lines Limited - India
- Truba Alam Manunggal Engineering.Tbk - Indonesia
- Jaiprakash Power Ventures ltd
- Makarim & Taira - Indonesia
- Maharashtra Electricity Regulatory Commission - India
- Neyveli Lignite Corporation Ltd, - India
- White Energy Company Limited
- Kaltim Prima Coal - Indonesia
- The Treasury - Australian Government
- Ministry of Mines - Canada
- Vedanta Resources Plc - India
- Indonesian Coal Mining Association
- Bukit Asam (Persero) Tbk - Indonesia
- Sojitz Corporation - Japan
- Therma Luzon, Inc, Philippines
- Kideco Jaya Agung - Indonesia
- Jindal Steel & Power Ltd - India
- Romanian Commodities Exchange
- IEA Clean Coal Centre - UK
- Wood Mackenzie - Singapore
- OPG Power Generation Pvt Ltd - India
- GVK Power & Infra Limited - India
- Parliament of New Zealand
- Miang Besar Coal Terminal - Indonesia
- Uttam Galva Steels Limited - India
- Offshore Bulk Terminal Pte Ltd, Singapore
- Filglen & Citicon Mining (HK) Ltd - Hong Kong
- AsiaOL BioFuels Corp., Philippines
- Kumho Petrochemical, South Korea
- Energy Link Ltd, New Zealand
- Alfred C Toepfer International GmbH - Germany
- Asia Pacific Energy Resources Ventures Inc, Philippines
- Orica Mining Services - Indonesia
- Holcim Trading Pte Ltd - Singapore
- Binh Thuan Hamico - Vietnam
- Formosa Plastics Group - Taiwan
- Price Waterhouse Coopers - Russia
- Oldendorff Carriers - Singapore
- Latin American Coal - Colombia
- Indo Tambangraya Megah - Indonesia
- Australian Commodity Traders Exchange
- Central Java Power - Indonesia
- Port Waratah Coal Services - Australia
- Asmin Koalindo Tuhup - Indonesia
- TeaM Sual Corporation - Philippines
- Directorate General of MIneral and Coal - Indonesia
- Indika Energy - Indonesia
- Attock Cement Pakistan Limited
- Bhushan Steel Limited - India
- SN Aboitiz Power Inc, Philippines
- Jorong Barutama Greston.PT - Indonesia
- New Zealand Coal & Carbon
- Semirara Mining Corp, Philippines
- Bukit Baiduri Energy - Indonesia
- Power Finance Corporation Ltd., India
- Vijayanagar Sugar Pvt Ltd - India
- Wilmar Investment Holdings
- Sakthi Sugars Limited - India
- Siam City Cement - Thailand
- Bharathi Cement Corporation - India
- Meenaskhi Energy Private Limited - India
- Parry Sugars Refinery, India
- Banpu Public Company Limited - Thailand
- ICICI Bank Limited - India
- Mjunction Services Limited - India
- Globalindo Alam Lestari - Indonesia
- Savvy Resources Ltd - HongKong
- Sindya Power Generating Company Private Ltd
- Star Paper Mills Limited - India
- LBH Netherlands Bv - Netherlands
- Ind-Barath Power Infra Limited - India
- Malabar Cements Ltd - India
- Pipit Mutiara Jaya. PT, Indonesia
- Meralco Power Generation, Philippines
- PowerSource Philippines DevCo
- Billiton Holdings Pty Ltd - Australia
- Bayan Resources Tbk. - Indonesia
- Kalimantan Lumbung Energi - Indonesia
- Cement Manufacturers Association - India
- Medco Energi Mining Internasional
- Antam Resourcindo - Indonesia
- Timah Investasi Mineral - Indoneisa
- Baramulti Group, Indonesia
- Leighton Contractors Pty Ltd - Australia
- Directorate Of Revenue Intelligence - India
- Manunggal Multi Energi - Indonesia
|
| |
| |
|