CAPITAL COSTS OF INDIAN COAL MINING PROJECT - AN ANALYST VIEW


By Mr Dipesh Dipu, Director - Consulting (Mining), Deloitte Touche Tohmatsu India Private Limited

The coal mining sector that has been opened partially through captive mining route has seen allocation of 208 coal blocks to private sector, government-owned power generation and other downstream companies. These coal blocks, however, have had limited success in terms of operationalisation on time and at budgeted costs. These have led to serious concerns for coal supplies for power generation sector in India.

One of the key concerns for the development of the coal mines in India has been the quantum of capital required which is the determinant of expected returns from investment perspective and the viability of the project in terms of affordability of power so generated. The capital costs for coal mining projects typically include costs of land, capital equipment and infrastructure to support mining and logistics. Project costs also include capitalised expenses for clearances and approvals that help the mining project take off.

Elements of Capital Costs
Cost of land typically means the cost of acquiring surface rights for coal bearing land for which allocation has been made by the appropriate authority. The recent social concerns that have generated a lot of debate in the country centre on the cost of land which the companies are willing to pay for acquiring surface rights. The recent trends indicate that the land values head northwards since the time of announcement of a project, which makes it challenging to estimate the cost of land. In states that have vast coal resources, the land acquisition issues have been observed to be acute. In Talcher and IB Valley coalfields of Orissa, for example, there are a large number of coal blocks proposed with massive capacities. In these coalfields, it may therefore be expected that land costs will be relatively higher for the coal mining projects. Costs of mining equipment largely dominate the project costs, although due to higher costs of land acquisitions, its proportions are likely to be revised downward. The costs of equipment, typically, are functions of geological characteristics, technology, mine design and requirement of coal processing. Equipment costs also include costs of electricity supply features, drainage systems, environmental management systems, surveillance systems and several others. The costs of construction of coal handling plants and railway siding are parts of support systems for evacuation of coal and if the coal project is relatively farther from the nearest railhead, the costs will be higher. For pit-head power project, the costs include the conveying system from mine to the coal handling system of the power project.

Key Determinants of Capital Costs
Technology is a key determinant of capital cost. Underground coal mining and surface (or opencast) mining has different requirements. In the underground mining methods, there are variants such as bord and pillar, longwall, shortwall and variants for thick seam mining such as horizontal slicing and inclined slicing; sub-level caving and others. The accesses to coal seams are made either through inclines (surface drifts) or vertical shafts, each of which may have substantially different capital cost. In surface mining methods, equipment selection largely determines the project costs - shovel-dumper combinations, dragline, bucket wheel excavators are mostly used in India. The geo-technical parameters like dip and strike length, inclination of seams, thickness of overburden layer, and stripping ratio are indicators of specifications of equipment required, which, in turn, indicate the capital costs.

Equipment selection, therefore, is at the core of the determination of capital costs. In surface mining, the equipment selection takes into account the geological features such as partings between coal seams and expected bench heights. These impact the selection of size of shovels and matching dumper sizes. In such cases, the natural economies of scale need not work and hence, the capital costs per tonne of production versus capacity or size of excavators is a non-linear function.

Apart from the excavators and hauling equipment, capital cost of surface mines also depend on size and number of drilling machines, which, in turn, are dependent on the hardness of the rock. For blasting, the use of site mix slurries or site mix emulsion explosives can eliminate the need to maintain a magazine at mine project and thus, lower the capital costs. Relatively softer rock formation, such as those of lignite, the drilling blasting processes may be replaced by continuous mining system as bucket wheel excavator. Rock fragmentation and the requirement of crushing (including secondary crushing and sizing) will determine the additional equipment required that have a direct bearing on capital costs.

Hydrological characteristics of mine indicate the requirement of drainage and pump capacities. These may be significant where the water tables are high and may have large capital costs required to keep the working faces prevented from being inundated.

Estimates
According to estimates, investments needed in surface coal mining in India are in the range of INR 1500-2100 (approximately US$ 31.65 - 44.30) per tonne of rated capacity. For example, investment in a one million tonne per annum capacity mine is expected to be INR 210 crore (approximately US$ 44.295 million). This estimation is based on a stripping ratio of 4:1 and appropriate adjustments can be made for projects that have higher or lower stripping ratios. This, however, is as good as only an estimate and for the purpose of evaluations and investment decision making purposes, nothing can substitute a detailed plan, including equipment selection and fleet size determination.

For underground mining, the estimates are in the range of INR 1900-2800 (approximately US$ 40.07 - 59.05) per tonne of rated capacity. These are estimated for project that are shallow (within 150 meters depth) and are worked with semi-mechanized bord and pillar mining methods.

Business models change contribution to capital costs
At a high level, project costs remain more or less unchanged, irrespective of ownerships and financing pattern. However, for the project developers, the project costs are not nearly as significant parameters as are the equity investments and returns thereof. The business models now being contemplated and implemented substantially reduces the equity investment and causes the owner of the coal mine to focus on alternative investments such as, those in power generation capacity building. Contract mining is fast catching up in India as the preferred mode for development and operations of mines. The business model of hiring contract mining companies for overburden removal and even mineral winning is not a recent innovation. There are a number of new projects being planned through contract routes. Even the traditional mining companies like, the Coal India Limited and SCCL have been contracting out their mining operations. The scope of work in many cases involves the contract mining company to use their own equipment to carry on mining activities, which reduces the capital expenditure requirement of the coal mine owner.

In a total outsourcing model, the owners contract out all the processes including statutory approvals and clearances, land acquisition, mine development and operations. The recently floated tenders of a few state government owned power utilities are proponents of this model. The prospective bidders for the contract mining projects are expected to conduct their own geo-technical assessments, study the feasibilities and bid for the long term contract. The owner pays for all of these as the coal is mined and delivered to the owner. This model reduces the capital expenditure required by the owner for the coal mine development to nearly negligible.

Other business model is that of equipment leasing, which reduces the initial capital cost substituting the same by a more manageable lease rentals. The finance and operating types of leases help the mining project to have substantially lower cash outflows at the beginning of the project and help match the revenues with the costs when the mine starts the production of coal.

Capital Cost Management
Costs form a part of the decision-making process and cannot be used as a stand-alone decision-making tool. For this reason, there are several frameworks that can be used as a decision-making tool for surface and underground mining projects. These frameworks incorporate thinking obtained from viewing costs as a holistic entity. Strategic Cost Management (SCM) provides the thinking behind viewing costs as a strategic issue. Life Cycle Costing (LCC) suggests making use of the Net Present Value (NPV) approach to account for the use of the capital equipment. The LCC approach incorporates a tool into the framework that ensures that the cost of technology (capital) is accounted for over its lifetime.

Costing is the processing of expenditures to calculate their cost to each project. A typical and an ideal cost management profile is given below:


As costs increase, performance gets impaired. When cost reduction is periodically initiated, it often results in a temporary cull of capabilities, directly impacting on future ability to deliver performance. Where cost reductions are achieved, performance often recovers temporarily, only for focus on proactive cost management to be lost, and for costs to begin to increase again. Without specific cost management action, this cycle can continue indefinitely.

It must be observed that the ability to influence project success and enhance value is greatest at the start of project evaluation and rapidly declines as a project advances towards implementation. In the same instance, the cost of change dramatically increases throughout each project evaluation stage. This suggests that the quality of the decision making in the early stages of project evaluation, primarily focused at capital costs, is critical to an optimal project outcome.

Cost Escalations and Indices
In coal mining projects, capital costs are dynamic and are inflated when the projects get delayed. Cost indexes provide a means of adjusting out-dated capital and operating cost information for the effects of inflation due to such delays. They are based on statistical averages of costs for specific items and time periods. There are the composite indexes for capital and operating costs for each of surface and underground coal mining and coal processing (preparation) operations, which are calculated taking into account several projects done in the past as well as taking economic indices into account. Indexes for specific cost centres, e.g., labour, equipment, transportation, fuel, explosives, tires, electric power, natural gas, and industrial chemicals are available, which are being used by the industry and the regulators to allow prudent escalations in the capital and the operating costs.

The above analysis was originally published on Infraline.

The views and opinions / conclusion expressed on this analysis is purely the writers’ own.

About Dipesh Dipu
Dipesh Dipu works as Director with Deloitte in the Energy and Resources consulting practice of the firm and anchors the Firm’s initiative in the mining and metals sectors. He is a mining engineering graduate from Indian School of Mines and is a Chartered Financial Analyst (CFA).

He has also done executive program in business management from Indian Institute of Management Calcutta. Dipesh has recently been awarded the Abheraj Baldota Gold Medal for the Young Mining Engineer of the Year 2007 by the Mining Engineers’ Association of India in recognition of his contributions in the improvement of mining industry in India.



If you believe an article violates your rights or the rights of others, please contact us.

Recent News

Wednesday, 14 September 11
GOVT SETS SEPTEMBER COAL REFERENCE PRICE AT $116.26 PER TON
COALspot.com - Ministry of Energy and Mineral Resources of Indonesia has set the September 2011 coal reference price at US$ 116.26 per ton slightly ...


Tuesday, 13 September 11
INDONESIAS COAL SECTOR EYES 2012 BOOM - JG
The Jakarta Globe, Indonesian English language News paper reported that, Coal production is set to surge next year as coal miners bolster their busi ...


Tuesday, 13 September 11
DRY BULK RALLY MAINTAINS MOMENTUM AT START OF THE WEEK - NIKOS ROUSSANOGLOU, HELLENIC SHIPPING
The dry bulk market kept its upward momentum at the start of the week, as the industry’s benchmark, the Baltic Dry Index (BDI) was up by 2.07% ...


Monday, 12 September 11
INDONESIAN GOVERNMENT HAS ALLOCATED MORE COAL FOR 2012
COALspot.com - Indonesian government has increased the domestic market obligation allocation to 82.07 million tons of coal for 2012, which is 4 perc ...


Saturday, 10 September 11
THE FREIGHT MARKET LIKELY TO BE FIRM NEXT WEEK - CAPT. REDDY
COALspot.com - The freight market continued the upward trend during last week with BDI crossing 1,800 points and closing at 1,838 points up by 5.63 ...


   1016 1017 1018 1019 1020   
Showing 5086 to 5090 news of total 6871
News by Category
Popular News
 
Total Members : 28,706
Member
Panelist
User ID
Password
Remember Me
By logging on you accept our TERMS OF USE.
Free
Register
Forgot Password
 
Our Members Are From ...

  • Vizag Seaport Private Limited - India
  • Mercuria Energy - Indonesia
  • Maharashtra Electricity Regulatory Commission - India
  • Miang Besar Coal Terminal - Indonesia
  • Port Waratah Coal Services - Australia
  • Iligan Light & Power Inc, Philippines
  • Tata Chemicals Ltd - India
  • Alfred C Toepfer International GmbH - Germany
  • Mjunction Services Limited - India
  • Straits Asia Resources Limited - Singapore
  • DBS Bank - Singapore
  • Eastern Energy - Thailand
  • Deloitte Consulting - India
  • SGS (Thailand) Limited
  • Dalmia Cement Bharat India
  • Coeclerici Indonesia
  • Meralco Power Generation, Philippines
  • PowerSource Philippines DevCo
  • Parliament of New Zealand
  • Coalindo Energy - Indonesia
  • GNFC Limited - India
  • SMG Consultants - Indonesia
  • Shree Cement - India
  • GAC Shipping (India) Pvt Ltd
  • Deutsche Bank - India
  • CoalTek, United States
  • Global Green Power PLC Corporation, Philippines
  • Wilmar Investment Holdings
  • Australian Commodity Traders Exchange
  • Carbofer General Trading SA - India
  • Price Waterhouse Coopers - Russia
  • Indogreen Group - Indonesia
  • Karbindo Abesyapradhi - Indoneisa
  • Idemitsu - Japan
  • Australian Coal Association
  • Directorate Of Revenue Intelligence - India
  • Sojitz Corporation - Japan
  • Savvy Resources Ltd - HongKong
  • Global Business Power Corporation, Philippines
  • Kaltim Prima Coal - Indonesia
  • London Commodity Brokers - England
  • Indian Energy Exchange, India
  • Bukit Asam (Persero) Tbk - Indonesia
  • Bangkok Bank PCL
  • Asia Cement - Taiwan
  • Kumho Petrochemical, South Korea
  • European Bulk Services B.V. - Netherlands
  • Heidelberg Cement - Germany
  • Cardiff University - UK
  • CNBM International Corporation - China
  • Uttam Galva Steels Limited - India
  • Jatenergy - Australia
  • Bank of China, Malaysia
  • GMR Energy Limited - India
  • Samtan Co., Ltd - South Korea
  • IOL Indonesia
  • Mintek Dendrill Indonesia
  • Vale Mozambique
  • Cebu Energy, Philippines
  • ETA - Dubai
  • Kartika Selabumi Mining - Indonesia
  • Bayan Resources Tbk. - Indonesia
  • Star Paper Mills Limited - India
  • Sree Jayajothi Cements Limited - India
  • APGENCO India
  • Meenaskhi Energy Private Limited - India
  • Parry Sugars Refinery, India
  • Bangladesh Power Developement Board
  • Freeport Indonesia
  • Ambuja Cements Ltd - India
  • SRK Consulting
  • LBH Netherlands Bv - Netherlands
  • Sarangani Energy Corporation, Philippines
  • Vitol - Bahrain
  • Interocean Group of Companies - India
  • Holcim Trading Pte Ltd - Singapore
  • JPMorgan - India
  • OCBC - Singapore
  • Xstrata Coal
  • Siam City Cement - Thailand
  • Larsen & Toubro Limited - India
  • Indian School of Mines
  • Kapuas Tunggal Persada - Indonesia
  • Platou - Singapore
  • Semirara Mining Corp, Philippines
  • ACC Limited - India
  • Latin American Coal - Colombia
  • IBC Asia (S) Pte Ltd
  • Arch Coal - USA
  • GHCL Limited - India
  • MEC Coal - Indonesia
  • Malabar Cements Ltd - India
  • Xindia Steels Limited - India
  • Gresik Semen - Indonesia
  • PLN Batubara - Indonesia
  • Eastern Coal Council - USA
  • Coal India Limited
  • The Treasury - Australian Government
  • Kideco Jaya Agung - Indonesia
  • IMC Shipping - Singapore
  • TeaM Sual Corporation - Philippines
  • Economic Council, Georgia
  • Barclays Capital - USA
  • JPower - Japan
  • Altura Mining Limited, Indonesia
  • Jindal Steel & Power Ltd - India
  • IEA Clean Coal Centre - UK
  • TGV SRAAC LIMITED, India
  • Pendopo Energi Batubara - Indonesia
  • Inspectorate - India
  • Standard Chartered Bank - UAE
  • Permata Bank - Indonesia
  • Trasteel International SA, Italy
  • Marubeni Corporation - India
  • Noble Europe Ltd - UK
  • The India Cements Ltd
  • Coastal Gujarat Power Limited - India
  • Commonwealth Bank - Australia
  • Indo Tambangraya Megah - Indonesia
  • OPG Power Generation Pvt Ltd - India
  • Kobe Steel Ltd - Japan
  • Pipit Mutiara Jaya. PT, Indonesia
  • KOWEPO - South Korea
  • Ministry of Mines - Canada
  • Baramulti Group, Indonesia
  • Leighton Contractors Pty Ltd - Australia
  • Rio Tinto Coal - Australia
  • SN Aboitiz Power Inc, Philippines
  • Coal Orbis AG
  • CESC Limited - India
  • Energy Development Corp, Philippines
  • PTC India Limited - India
  • Fearnleys - India
  • Pinang Coal Indonesia
  • Jorong Barutama Greston.PT - Indonesia
  • Thermax Limited - India
  • Core Mineral Indonesia
  • MS Steel International - UAE
  • ANZ Bank - Australia
  • ASAPP Information Group - India
  • Dong Bac Coal Mineral Investment Coporation - Vietnam
  • Chettinad Cement Corporation Ltd - India
  • World Bank
  • Edison Trading Spa - Italy
  • Infraline Energy - India
  • Thomson Reuters GRC
  • Shenhua Group - China
  • Global Coal Blending Company Limited - Australia
  • Makarim & Taira - Indonesia
  • GVK Power & Infra Limited - India
  • WorleyParsons
  • Cosco
  • Central Electricity Authority - India
  • Vedanta Resources Plc - India
  • Georgia Ports Authority, United States
  • Singapore Mercantile Exchange
  • International Coal Ventures Pvt Ltd - India
  • UOB Asia (HK) Ltd
  • Wood Mackenzie - Singapore
  • Attock Cement Pakistan Limited
  • Bulk Trading Sa - Switzerland
  • White Energy Company Limited
  • Mitra SK Pvt Ltd - India
  • Bank of America
  • Inco-Indonesia
  • Anglo American - United Kingdom
  • BNP Paribas - Singapore
  • Thailand Anthracite
  • Geoservices-GeoAssay Lab
  • Energy Link Ltd, New Zealand
  • Electricity Authority, New Zealand
  • Aditya Birla Group - India
  • Mechel - Russia
  • Banpu Public Company Limited - Thailand
  • Bank of Tokyo Mitsubishi UFJ Ltd
  • Thiess Contractors Indonesia
  • Binh Thuan Hamico - Vietnam
  • Agrawal Coal Company - India
  • Maruti Cements - India
  • Cemex - Philippines
  • UBS Singapore
  • Glencore India Pvt. Ltd
  • Credit Suisse - India
  • Indika Energy - Indonesia
  • Gujarat Electricity Regulatory Commission - India
  • Merrill Lynch Bank
  • ICICI Bank Limited - India
  • TNB Fuel Sdn Bhd - Malaysia
  • South Luzon Thermal Energy Corporation
  • KPMG - USA
  • globalCOAL - UK
  • Globalindo Alam Lestari - Indonesia
  • Ind-Barath Power Infra Limited - India
  • Ince & co LLP
  • Asian Development Bank
  • Bukit Makmur.PT - Indonesia
  • Oldendorff Carriers - Singapore
  • India Bulls Power Limited - India
  • Riau Bara Harum - Indonesia
  • Reliance Power - India
  • Sucofindo - Indonesia
  • AsiaOL BioFuels Corp., Philippines
  • Maersk Broker
  • Essar Steel Hazira Ltd - India
  • Bhatia International Limited - India
  • McKinsey & Co - India
  • Lanco Infratech Ltd - India
  • Timah Investasi Mineral - Indoneisa
  • Manunggal Multi Energi - Indonesia
  • Gujarat Sidhee Cement - India
  • Kobexindo Tractors - Indoneisa
  • Romanian Commodities Exchange
  • Russian Coal LLC
  • Kohat Cement Company Ltd. - Pakistan
  • Madhucon Powers Ltd - India
  • Berau Coal - Indonesia
  • Vijayanagar Sugar Pvt Ltd - India
  • PLN - Indonesia
  • Maheswari Brothers Coal Limited - India
  • Surastha Cement
  • TANGEDCO India
  • The State Trading Corporation of India Ltd
  • Clarksons - UK
  • J M Baxi & Co - India
  • Thai Mozambique Logistica
  • Gupta Coal India Ltd
  • Coaltrans Conferences
  • ING Bank NV - Singapore
  • Adani Power Ltd - India
  • Offshore Bulk Terminal Pte Ltd, Singapore
  • Tamil Nadu electricity Board
  • VISA Power Limited - India
  • HSBC - Hong Kong
  • Samsung - South Korea
  • PetroVietnam
  • Indonesian Coal Mining Association
  • SASOL - South Africa
  • PetroVietnam Power Coal Import and Supply Company
  • Petrosea - Indonesia
  • Minerals Council of Australia
  • Qatrana Cement - Jordan
  • Bharathi Cement Corporation - India
  • Intertek Mineral Services - Indonesia
  • Siam City Cement PLC, Thailand
  • KPCL - India
  • Tanito Harum - Indonesia
  • Petrochimia International Co. Ltd.- Taiwan
  • Dr Ramakrishna Prasad Power Pvt Ltd - India
  • Power Finance Corporation Ltd., India
  • Runge Indonesia
  • CCIC - Indonesia
  • CIMB Investment Bank - Malaysia
  • Mercator Lines Limited - India
  • EMO - The Netherlands
  • Directorate General of MIneral and Coal - Indonesia
  • SMC Global Power, Philippines
  • Simpson Spence & Young - Indonesia
  • Krishnapatnam Port Company Ltd. - India
  • Coal and Oil Company - UAE
  • GB Group - China
  • Barasentosa Lestari - Indonesia
  • Karaikal Port Pvt Ltd - India
  • RBS Sempra - UK
  • Platts
  • Therma Luzon, Inc, Philippines
  • McConnell Dowell - Australia
  • NALCO India
  • IHS Mccloskey Coal Group - USA
  • Orica Australia Pty. Ltd.
  • Sindya Power Generating Company Private Ltd
  • Asmin Koalindo Tuhup - Indonesia
  • Truba Alam Manunggal Engineering.Tbk - Indonesia
  • Bukit Baiduri Energy - Indonesia
  • Aboitiz Power Corporation - Philippines
  • Salva Resources Pvt Ltd - India
  • Jaiprakash Power Ventures ltd
  • Kalimantan Lumbung Energi - Indonesia
  • Thriveni
  • Central Java Power - Indonesia
  • Arutmin Indonesia
  • Merrill Lynch Commodities Europe
  • Goldman Sachs - Singapore
  • Asia Pacific Energy Resources Ventures Inc, Philippines
  • Rashtriya Ispat Nigam Limited - India
  • Videocon Industries ltd - India
  • Africa Commodities Group - South Africa
  • EIA - United States
  • U S Energy Resources
  • NTPC Limited - India
  • Ministry of Transport, Egypt
  • Toyota Tsusho Corporation, Japan
  • Moodys - Singapore
  • Gujarat Mineral Development Corp Ltd - India
  • Argus Media - Singapore
  • Ceylon Electricity Board - Sri Lanka
  • Sinarmas Energy and Mining - Indonesia
  • Grasim Industreis Ltd - India
  • Independent Power Producers Association of India
  • Japan Coal Energy Center
  • Posco Energy - South Korea
  • San Jose City I Power Corp, Philippines
  • Petron Corporation, Philippines
  • Humpuss - Indonesia
  • Bhushan Steel Limited - India
  • Malco - India
  • Orica Mining Services - Indonesia
  • Billiton Holdings Pty Ltd - Australia
  • TRAFIGURA, South Korea
  • Sical Logistics Limited - India
  • Indorama - Singapore
  • Renaissance Capital - South Africa
  • Filglen & Citicon Mining (HK) Ltd - Hong Kong
  • Tata Power - India
  • Medco Energi Mining Internasional
  • Borneo Indobara - Indonesia
  • Britmindo - Indonesia
  • Planning Commission, India
  • New Zealand Coal & Carbon
  • Mitsui
  • Indian Oil Corporation Limited
  • SUEK AG - Indonesia
  • Total Coal South Africa
  • Indonesia Power. PT
  • Adaro Indonesia
  • Ministry of Finance - Indonesia
  • TNPL - India
  • bp singapore
  • Peabody Energy - USA
  • Maybank - Singapore
  • Chamber of Mines of South Africa
  • Semirara Mining and Power Corporation, Philippines
  • The University of Queensland
  • Sakthi Sugars Limited - India
  • Electricity Generating Authority of Thailand
  • World Coal - UK
  • Bhoruka Overseas - Indonesia
  • Mitsubishi Corporation
  • Metalloyd Limited - United Kingdom
  • Bahari Cakrawala Sebuku - Indonesia
  • Cement Manufacturers Association - India
  • Cargill India Pvt Ltd
  • Rudhra Energy - India
  • BRS Brokers - Singapore
  • Neyveli Lignite Corporation Ltd, - India
  • KEPCO - South Korea
  • Formosa Plastics Group - Taiwan
  • Panama Canal Authority
  • Lafarge - France
  • Ernst & Young Pvt. Ltd.
  • GN Power Mariveles Coal Plant, Philippines
  • Kepco SPC Power Corporation, Philippines
  • Enel Italy
  • Antam Resourcindo - Indonesia
  • Cigading International Bulk Terminal - Indonesia
  • PNOC Exploration Corporation - Philippines